Participant Categories, Unit States, and Recall Times

Mandatory if Available Recall Times are only mandatory where recall information applies. NULL submissions are valid if recall is not possible.

The following table describes the registered participant categories, unit states, and recall times fields for MT PASA Medium Term Projected Assessment of System Adequacy. A 24-month supply demand forecast, published weekly, with daily resolution. Offers.

Registered participant category

DUID connection type

Unit state

Unit state type

Outage type

Recall time

Weekly energy limit

PASA availability

Scheduled Generator

SGU

Inactive reserve (InactiveReserve)

Deactivated Shutdown

Economic

Mandatory

null or >= 0

0

SGU

Mothballed (Mothballed)

Deactivated Shutdown

Economic

Mandatory

null or >= 0

0

SGU

Retired

Deactivated Shutdown

Economic

None

null or >= 0

0

SGU

No deratings (NoDeratings)

Available

When submitted MT PASA Availability is dependable capacity not just maximum capacity, also includes seasonal derating

None

null or >= 0

>0

SGU

Basic planned deratings (DeratingPlanBasics)

Available

Physical

Optional

null or >= 0

>0

SGU

Derating plan extend (DeratingPlanExtend)

Available

Physical

Optional

null or >= 0

>0

SGU

Unplanned forced deratings (DeratingUnplanForced)

Available

Physical

Optional

null or >= 0

>0

SGU

Unplanned maintenance deratings (DeratingUnplainMaint)

Available

Physical

Optional

null or >= 0

>0

SGU

Basic planned outage (OutagePlanBasic)

Unavailable

Physical

Optional

null or >= 0

0

SGU

Extended planned outage (OutagePlanExtend)

Unavailable

Physical

Optional

null or >= 0

0

SGU

Unplanned forced outage (OutageUnplanForced)

Unavailable

Physical

Optional

null or >= 0

0

SGU

Unplanned maintenance outage (OtageUnplanMaint)

Unavailable

Physical

Optional

null or >= 0

0

Integrated Resource Provider

BDU

SGU

Inactive reserve (InactiveReserve)

Deactivated Shutdown

Economic

Mandatory

null or >= 0

0

BDU

SGU

Mothballed (Mothballed)

Deactivated Shutdown

Economic

Mandatory

null or >= 0

0

BDU

SGU

Retired (Retired)

Deactivated Shutdown

Economic

None

null or >= 0

0

BDU

SGU

No deratings (NoDeratings)

Available

When submitted MT PASA Availability is dependable capacity not just maximum capacity, also includes seasonal derating

None

null or >= 0

>0

BDU

SGU

Basic planned deratings (DeratingsPlanBasic)

Available

Physical

Optional

null or >= 0

>0

BDU

SGU

Derating plan extend (DeratingPlanExtend)

Available

Physical

Optional

null or >= 0

>0

BDU

SGU

Unplanned forced deratings (DeratingUnplanForced)

Available

Physical

Optional

null or >= 0

>0

 

BDU

SGU

Unplanned maintenance deratings (DeratingUnplanMaint)

Available

Physical

Optional

null or >= 0

>0

BDU

SGU

Basic planned outage (OutagePlanBasic)

Unavailable

Physical

Optional

null or >= 0

0

 

BDU

SGU

Extended planned outage (OutagePlanExtend)

Unavailable

Physical

Optional

null or >= 0

0

BDU

SGU

Unplanned forced outage (OutageUnplanForced)

Unavailable

Physical

Optional

null or >= 0

0

 

BDU

SGU

Unplanned maintenance outage (OutageUnplanMaint)

Unavailable

Physical

Optional

null or >= 0

0

Market Customer

SLU

Optional

null or >= 0

>=0

Market Network Service Provider

SNS

Optional

Null

>=0

Integrated Resource Provider

SLU

Optional

null or >= 0

>=0

For Production Units, unit state is mandatory and cannot be NULL.